Bangkok--Jul 31--Ratchaburi Electricity Generating Holding plc (RATCH)
Ratchaburi Electricity Generating Holding plc (RATCH) has announced that the transfer of the Ratchaburi combined cycle power plant s Block One and Block Two from the Electricity Generating Authority of Thailand (EGAT) to Ratchaburi Electricity Generating Co., Ltd., RATCH's subsidiary, has been rescheduled from August 31 to October 31, 2001. This is due to uncompleted performance testing of the diesel-oil firing of the two Blocks.
As a result of this rescheduling, RATCH has revised its estimated operating results for the 2001 fiscal year. RATCH's net profits are now anticipated to be 3,275.82 million baht, or 2.26 baht per share, which is 6.43% lower than the previous estimate of 3,500.99 million baht, or 2.41 baht per share.
The company's revenues for the year are expected to be 21,541.32 million baht, while expenses are anticipated to be 18,442.36 million baht. However, the company will receive compensation from EGAT amount of 176.86 million baht, or 88.43 million baht per month, due to the late transfer of the two combined cycle Blocks.
"We are confident that EGAT's delivery can be achieved by October 2001. Gas-fueled testing for gas turbine generators and 72 consecutive hours capability testing for combined cycle mode full load has already been completed; only diesel-oil firing are currently undergoing the testing process. After that, capability and performance tests will be undertaken involving a trial run test for 30 consecutive days. After the completion of all tests, commercial operation date will start," said Boonchoo Direksathapon, Managing Director, Ratchaburi Electricity Generating Holding plc.
For more information, please contact:
Ratchaburi Electricity Generating Holding Plc
Boonsom Chan-umroung
Tel: +0 2978 5061
Fax: +0 2937 9321
email: [email protected] End.
-AN-