Mr.Songkiert Tansamrit, Director of the Corporate Relations Department of the Petroleum Authority of Thailand (PTT), revealed details of forest conditions in the National Park, through which the Yadana Gas Pipeline will be laid after the Cabinet passed a resolution approving PTT to use the area for the purpose. The approval was granted for PTT to temporarily use the 105-rai area during the construction. The gas pipeline will pass through 4 sections of forest in the Sai Yok National Park of 20-meter wide over a total length of 8.4 kilometers, with the following details:
1. The plain at the slope of Ti Pue Hill (KP.43+101 - KP.47+510) of 4.5-kilometer long covering the area of 56.25 rais is the watershed area class 1 and 2. The area is the inspection road; on both sides are mostly mixed deciduous forest and bamboo forest. (The line pipe will be laid on the inspection road.)
2. Baan Wang Nok Kaew (KP.68+800 - KP.69+250) of 0.45-kilometer long covering the area of 5.6 rais is the watershed area class 4 and 5; the area is the plain and no longer has forest condition. The area is now all occupied by villagers doing cultivation.
3. Kilometer 76 of Highway No.323 (new) (KP.74+500 - KP.77+500) of 3-kilometer long covering the area of 37.5 rais is the watershed area class 4, most of which is plain and the slope of the hill close to Highway No.323 (new), and no longer has forest condition.
4. Baan Phu Ong Ka (KP.74+500 - KP.77+500) of 0.45-kilometer long, covering the area of 5.6 rais is the watershed area class 3; the area is the plain at the slope of the hill, mostly bamboo forest.
The Corporate Relations Director added that PTT's request to use forest area has been continuously implemented, starting with the Environmental Impact Assessment in 1995. The Royal Forestry Department also severally sent officials for field survey. The line pipe laid through 50-kilometer of forest, 6 kilometers of which are lush, in the Huay Kha Yeng Reserves Forest in Khao Takua but not in the National Park. According to the Action Plan, PTT would reduce the width of construction area from 20 to 12 meters and special rechniques differing from the plain area will be utilized.
The impact during the construction period will last about 5-6 months and the construction will be finished in only one dry season. After the lowering-in and backfilling of line pipe, PTT will accelerate the rehabilitation plan. Above all, no roads will be constructed over the line. The impact will thus be temporary. End.